| Nilefos Minerals Limited: Phase I: Mining Capital cost | |||
| units | cost/unit US$ | US$ | |
| 13.5m3 Hydraulic Shovel | 1 | 3,100,000 | 3,100,000 |
| 777 RD Truck | 1 | 1,040,000 | 1,040,000 |
| 631 Scraper | 1 | 600,000 | 600,000 |
| D-9 Dozer | 1 | 829,000 | 829,000 |
| 824 RT Dozer | 1 | 550,000 | 550,000 |
| 16H Grader | 1 | 610,000 | 610,000 |
| Water Truck | 1 | 100,000 | 100,000 |
| Fuel/Lube Truck | 1 | 180,000 | 180,000 |
| Service Truck | 1 | 100,000 | 100,000 |
| Light Plants | 1 | 20,000 | 20,000 |
| Pumps | 2 | 25,000 | 50,000 |
| 50kta Gravel Plant | 1 | 350,000 | 350,000 |
| total technical | 7,529,000 | ||
| Contingency % | 15% | ||
| Contingency US$ | 1,129,350 | ||
| Total including contingency | 8,658,350 | ||