| Nilefos Minerals Limited: Phase I: Beneficiation Capital cost as per Delkor scope | ||
| S.No | Description | US$ |
| 1 | Design & engineering 50 tph hour plant as mentioned in the scope of work | 583,333 |
| 2 | Price for supply of equipments as per process description and specifications in our offer | 6,583,283 |
| 3 | Price for supply of building structures, equipment supporting structures, walk ways, platforms and stairways | 775,615 |
| 4 | Piping and drain valves | 168,107 |
| 5 | Supply of Sub station | 275,000 |
| 6 | Supply of LT panel MCC, cables and accessories | 320,296 |
| 7 | master control with PLC and SCADA system | 88,150 |
| 8 | DG sets 2 x 750 KVA and 1 x 250 KVA | 484,615 |
| 8 | Spares for 2 years operations | 677,167 |
| 9 | Charges for supervision for erection & commissioning of the plant | 512,980 |
| Total technical | 10,468,546 | |
| Contingency % | ||
| Contingency US$ | - | |
| Total including contingency | 10,468,546 | |