Nilefos Minerals Limited: Phase I: Beneficiation Capital cost as per
Delkor scope |
S.No |
Description |
US$ |
1 |
Design & engineering 50 tph hour plant as mentioned in the scope of
work |
583,333 |
2 |
Price for supply of equipments as per process description and
specifications in our offer |
6,583,283 |
3 |
Price for supply of building structures, equipment supporting structures,
walk ways, platforms and stairways |
775,615 |
4 |
Piping and drain valves |
168,107 |
5 |
Supply of Sub station |
275,000 |
6 |
Supply of LT panel MCC, cables and accessories |
320,296 |
7 |
master control with PLC and SCADA system |
88,150 |
8 |
DG sets 2 x 750 KVA and 1 x 250 KVA |
484,615 |
8 |
Spares for 2 years operations |
677,167 |
9 |
Charges for supervision for erection & commissioning of the plant |
512,980 |
|
|
|
Total technical |
10,468,546 |
|
Contingency % |
|
|
Contingency US$ |
- |
|
Total including contingency |
10,468,546 |
|
|
|
|