VOLUME I: EXECUTIVE SUMMARY: TABLE OF CONTENTS
NB: si vous passez en edition word, vous aurez ce document avec des signets pour consultation rapide

    1.0         INTRODUCTION

    2.0         RESOURCES

    3.0         MINING AND RESERVES

    4.0         PROCESSING

    5.0         INFRASTRUCTURE

    6.0         ENVIRONMENTAL REVIEW

    7.0         PROCESS ALTERNATIVES

    8.0         CONCEPTUAL DEVELOPMENT PLANS: PRODUCTION, COSTS & INVESTMENTS

    9.0         VALUATION

LIST OF FIGURES

    2-1         Location of Claims, Ferrobamba, Tintaya

            Metallogenic Belt  2.2

    2-2         Geologic Map of Tintaya Area         2.4

    3-1         Tintaya District Map         3.3

    4-1         Processing Facilities Layout, Tintaya Mine4.3

    4-2         Tintaya Mine, Main Tailings Dam4.7

    5-1         Tintaya Site Map         5.2

LIST OF TABLES

       2-1            Geologic Resource            2.6

       2-2            Preliminary Ore Reserve Calculations for the Bambas Region 2.11

       3-1            Mineable Reserves as of September 1, 1993 3.4

       3-2            Conceptual Production Schedule.8

       8-6            Concentrator Costs            8.9

       8-7            General, Administrative & Marketing Costs8.10

       8-8            Copper Oxide Production & Costs8.11

       8-9            Submerged Combustion Smelting - Production & Costs8.13

       9-1            Summary of Operating Parameters for Cases 1, 2 and 3 9.3

       9-2            Net Present Value  9.4

       9-3            Results of Sensitivity Analysis9.5

       9-4            Comparable Transactions            9.7

       9.5            Comparable Copper properties exchanged from 1992-19939.9

TINTAYA S.A.

Pincock, Allen & Holt‑A Division of Hart Crowser Inc. (PAH), in association with SVS Ingenieros of Peru, undertook a complete technical review of the operations of Tintaya S.A. for the purpose of identifying areas of potential new developments and conducting an economic evaluation of the company. It was the conclusion of PAH that Tintaya represents a significant on‑going operation, with a capacity to produce more than 50 000 tonnes of fine copper annually during the next 15 years. Significant investment will be required for the development of new mining areas. However, the quantity and quality of the reserves justifies this investment.

Tintaya is, at 0.57 USD/lb , a medium cost producer and is relatively protected from price downturns, due to its mining conditions and technology. The introduction of new technologies, if technically and economically feasible, could add substantial value to the company's products and reduce its unit operating costs significantly, thereby placing Tintaya in the lower cost producers.

Acid leaching followed by solvent extraction and electro winning of copper from oxide ores (SX/EW), represents one development which would be profitable due to lower costs. A second development would be the construction of a submerged combustion smelter, near the site, to serve the interests of Tintaya and other neighbouring properties. Such a development would enable to decrease costs more drastically by reducing transport costs. However, this is by nature, a more speculative opportunity due to the capital cost involved and would require strategic decisions by the future owner, alone or in joint venture with other interested parties, including Peruvian Government.

Based on discounted cash flow projections using realistic costs of production and receipts from sales of concentrates, and comparing with other transactions in similar conditions, PAH has determined a range of market values for Tintaya S.A. which lie between 43 and 90 Million USD, depending on the rate of return that may be required from the venture.

1.0 INTRODUCTION

This report presents the findings of a valuation study completed by Pincock, Allen & Holt - A Division of Hart Crowser Inc. (PAH) and SVS Ingenieros for Empresa Minera Especial Tintaya S.A. (Tintaya). The study is to be used as the foundation for the subsequent privatization of the company.

There are five principal objectives of the study:

     To certify at international standards the known mineral reserves.

     To provide a full technical evaluation of the company's current and planned operations.

     To identify potential areas of new or additional value. This includes the development of new mining areas as well as the implementation of new technologies for improved mineral processing.

     To ascertain the company's competitive position among the world copper producers.

     To value the company based on its current and future potential.

To achieve these objectives an encompassing scope of work was defined. This included visits by a multi-disciplinary team of geologists, engineers and economists to all facilities under control of the company. Detailed reviews were accomplished with the assistance of Tintaya counterpart personnel.

Reserve data was collected and assembled in a computerized database for analysis with PAH's proprietary modelling software MicroMODEL and PolyMAP. This allowed for a full certification of reserves. A preliminary development plan was defined for the orderly mining of the known areas of mineralization at the Tajo, Chabuca Este, Chabuca Sur and Coroccohuayco. All areas that can easily provide feed for the existing concentrator. A review of concentration facilities was completed along with the preparation of conceptual level studies for the implementation of sulfide smelting and oxide treatment facilities.

Additionally, promising exploration areas outside the immediate Tintaya area were reviewed. This includes the areas know as the Bambas, Katanga, Winococha and others.

       Report Organization

This report is organized into four volumes.

Volume I - Executive Summary - This volume provides a broad overview of the project and a summary of major findings.

Volume II - Technical Evaluation - This volume provides a comprehensive analysis of current and potential operation. Detailed production, cost and investment scenarios are presented for future operations under a variety of conditions.

Volume III - Commercial Evaluation - This volume contains an analysis of current and projected market conditions and an evaluation of Tintaya's competitive position.

Volume IV - Economic/Financial Evaluation - This volume presents an analysis of the company's  recent financial performance. It also presents the final valuation of the company based on expected operational conditions.

       Project Team

The PAH project team consisted of the following members:

     William Pincus               Project Manager

     Ulrich Petersen          Geologist

     George Armbrust          Geologist

     Mark Stevens          Geologist

     Robert Sandefur                 Geostatistician

     Steven Milne               Mine Engineer

     Donald Tschabrun                 Geological Engineer

     Richard Addison          Process Engineer

     T. F. Izzo                    Process Engineer

     Christopher Davie              Process Engineer

     L. Pat Gochnour                Environmental Specialist

     Antonio Samaniego              Geotechnical Engineer

     Cesar Vidal                  Geologist

     Juan Paniagua               Electrical Engineer

     Miguel Verimendi                Civil Engineer

     Lee Aga                   Draftsman

     Sandy Prebynski               Project Secretary

       Acknowledgements

PAH would like to acknowledge the engineers and staff of Tintaya who worked long and hard to make this a successful project. In particular it would like to acknowledge the members of Tintaya's Special Privatization Committee (CEPRI): Luis Moran, Francisco Fernandez and Juan Assereto.  Special mention is also made of Oscar Calero and Pelayo Miranda. Finally, PAH would like to acknowledge e services of its Lima representative Guillermo Alvarez-Calderon.

2.0 RESOURCES

Geology

The Tintaya mining district is located near the center of Tintaya-Ferrobamba "Copper Belt," a north-northeast trending polymetallic metallogenic belt that extends at least from the vicinity of the city of Puno through the department of Apurimac. This 500 kilometer long belt is about 50 kilometers wide and contains a variety of copper, copper-gold, gold, iron, and lead-zinc-silver ore deposits. Copper and copper‑gold deposits predominate in its central part (i.e., where this belt crosses the departments of Cuzco and Apurimac . The largest copper and copper-gold deposits in this central region are of the skarn type.

The Tintaya ore deposits are of the skarn type and are located in the south-eastern end of that portion of the metallogenic belt which contains most of the copper and copper-gold ore deposits. Other mining properties of the Peruvian Government which form part of the "privatization package" reviewed in this report occur in the central part (e.g., Winicocha) and in the northern end (e.g., Ferrobamba, Chalcobamba, Charcas and Sulfobamba) of the copper-gold skarn region (Figure 2-1).

The important copper-gold and iron skarn ore deposits of the region formed in the contact zones of the Upper Cretaceous granodiorite and monzonite intrusions with the Middle Cretaceous Ferrobamba limestone.

The Tintaya mining district is located in a part of the aforementioned polymetallic metallogenic belt where the Mesozoic sediments crop out in relatively small areas that are surrounded regionally by the overlying Tertiary and Pleistocene volcanic rocks, and by widespread alluvial sediments. In these areas, several Cretaceous-Lower Tertiary igneous intrusions invaded the Ferrobamba limestone and generated

Figure 2-1

skarns with copper-gold mineralization. Presently, Tintaya is the largest, best known and most mined of these areas (Figure 2-2). However, similar skarn mineralization has been discovered nearby at Coroccohuayco (7.5 kilometers to the southeast), at Ccayo-Huinicunca (13 kilometers to the west), at Ccoyme-Fito (3 kilometers to the east), at Atalaya (10 kilometers to the southwest), and at Quechuas (5 kilometers to the east‑southeast). At the latter locality, there is also evidence of porphyry copper type mineralization.

The Tintaya area is best described by referring to geographic designations that evolved as geological mapping, geophysical exploration, exploratory drilling, development and mining revealed new mineralized zones. Mining started at the site of the present open pit, referred to as "Tajo". About 1.5 kilometers to the east is a zone of abundant outcrops of Ferrobamba limestone that has been partly converted to skarn and mineralized. This zone is referred to as "Chabuca." A relatively thin band of Ferrobamba limestone and skarn outcrops known as "Chabuca Este," connect the Tajo and Chabuca zones. Both north and south of Chabuca there are extensive outcrops of Ferrobamba limestone with subordinate proportions of skarn and mineralization. These zones are referred to as "Chabuca Norte" and Chabuca Sur," respectively. To the east of Tajo there are also evidences of limestone, skarn and mineralization, which are known as "Zona Nueva Este." The Coroccohuayco area is located approximately 13 kilometers by road southeast of the Tajo.

Resource Modelling - Tintaya Area

PAH developed four separate computer block models for each of Tintaya's deposit areas, including 1) Tajo Tintaya/Inflexion/Zona Nueva, 2) Chabuca Este, 3) Chabuca Sur, and 4) Coroccohuayco.  Significant overlap occurs between the Tajo and the Chabuca Este models, and between the Chabuca Este and Chabuca Sur models, due

Figure 2-2

to the deposits general proximity to one another. The Coroccohuayco model occurs 7.5 kilometers southeast of the other models.

The resource for the four Tintaya project areas evaluated by PAH have been tabulated at total copper cutoff grades that are similar to those used to determine the open pit and underground reserve. This allows for direct comparison between the resource and subsequent reserve. The geologic resource includes all material in the model at the specified cutoff grade, without regard to mineability.

In addition, PAH has included as resources the Chabuca area and the Oxide Stockpile, as estimated by Tintaya. The Chabuca area has been extensively drilled and consists largely of oxide material. The oxide stockpile includes oxide material mined from the Tajo and is located northeast of the pit, adjacent to the processing facilities. The stockpile is separated into three areas: 1) high grade oxide averaging 2.62% copper, 2) medium grade oxide averaging 1.61% copper, 3) low grade oxide averaging 0.93% copper.

The sum of the sulfide resources in the Tintaya project areas is 61,390,000 tonnes at an average grade of 2.50% copper. The sum of the oxide resources in the Tintaya project areas is 23,542,000 tonnes at an average grade of 2.15% copper. The resource by project area is presented in Table 2-1.

For the Tajo area, the resource is tabulated for mineralization that occurs below the current pit surface, as derived from the August 30, 1993 surveyed pit points. The Tajo resource has been divided into three subcategories, in keeping with that presented by previous Tintaya tables. The Tajo ultimate pit resource is the resource contained within PAH's ultimate designed pit and is equal to the reserve for this pit configuration (bottom at 3,845 meters). The Tajo resource outside the pit is the

Table 2-1

resource that occurs outside of the ultimate designed pit above the 3,845 meter level. The Tajo resource below the pit is the resource that occurs below the bottom level of the ultimate designed pit below the 3,845 meter level. In addition, Tintaya reports a stockpile of oxide material containing 9,860,110 tonnes at a 2.00% copper grade.

In order to distinguish the Tajo resource from the Chabuca Este resource, as they are on the same mineralized zone, the 1,235,900 East coordinate was chosen as the boundary between the resource areas. To the east, the resource has been included in the Tajo. To the west, the resource has been included in Chabuca Este.

In preparing the resource estimate, PAH has followed standard North American engineering practices and has used the Society for Mining, Metallurgy, and Exploration (SME) guidelines for resource and reserve estimation (Working Paper Number 79). On this basis, PAH reclassified Tintaya's reserve to a resource. The following discussion reflects this reclassification.

Tintaya has previously generated resource estimates for the Tajo, Chabuca Este, Chabuca Sur, and Coroccohuayco project areas. For this study, PAH used an estimation methodology similar to that used by Tintaya. PAH's estimate differs from that of Tintaya largely because PAH used different cutoff grades for reporting purposes. Differences also occurred because of the selection of different boundaries for resource areas. Other differences reflected small variations in the basic estimation methodologies.

For comparison purposes, PAH tabulated their resources at the same cutoff grades as Tintaya. The results showed that for sulfide material Tintaya was quite close to the PAH estimate, with PAH estimating four% more total pounds of copper resource. For oxide material, the Tintaya estimates were somewhat higher than PAH's reflecting some differences in the rock model geology.

PAH conducted a reconciliation of the PAH polygonal model for the Tajo area with the total production to date as provided by Tintaya production reports. The results indicated that relative to reported production this modelling methodology tends to underestimate tonnage and overestimate grade. However, total production in terms of in-place pounds of copper is quite close. On the basis of this reconciliation, PAH believes that the modelling methodology is suitable for further mine planning.

Exploration Potential - Tintaya Area

The history of exploration in the Tintaya area has shown that the sequence of systematic geological mapping and interpretation, sampling, geophysical and geochemical surveys and drilling has found amounts of ore well beyond those surmised initially on the basis of surface indications. In addition to following the obvious strategy of continuing to enlarge the reserve in the known ore bodies by drilling their "open ends," there appear to be several other exploration objectives, as discussed below.

One target is the area south of Chabuca Este. Tintaya recently completed a diamond drilling program consisting of 11 holes for a cumulative length of 1,418 meters at a drill hole spacing of 100 to 200 meters. The drilling program defined a broad syncline with diorite in the core overlying limestone, and skarn mineralization developed at the contact between the two rock types. The mineralized intervals are 3 to 17 meters thick, and contain 0.4 to 3.1% total copper. Tintaya estimates a potential for approximately 9 million tonnes of mineralized material in this area. The depth to this mineralized horizon is 50 to 150 meters.

Another target is the area northwest of Chabuca Este, approximately 1,500 meters west of the Tintaya pit. Tintaya recently completed a five-hole drilling program for a cumulative length of 1,318 meters. The area is considered to lie in a synclinal basin with a monzonite core overlying limestone. Two orebodies have been identified; the East Body at Chabuca Norte, and the West Sector at Chabuca Este. The drilling indicates that copper mineralization extends to depth of at least 350 meters near the edge of the basin, but holes were not deep enough to intercept the monzonite-limestone contact in the central part of the basin. Intervals of skarn mineralization were encountered within the monzonite. Tintaya estimates a potential for 9 million tonnes of mineralized material from the recent drilling. Additional deeper drilling is needed to test the monzonite-limestone contact.

Additional potential occurs at depth in the Tajo area. The current model has an artificial bottom at the 3,845 elevation, as this was the lowest level of the Tintaya's digitized geology. Below this level the data does not define the skarn body and, as a result, grade values were not assigned in the model. Some drilling does continue below this level and indicates the presence of skarn mineralization with ore grade copper values. This mineralization will add to the resource base and needs to be further defined.

The Coroccohuayco deposit limits have not been adequately defined and will require further drilling. As a result, the deposit limits may be extended as a result thereby increasing the contained resource.

In order to make exploration more efficient, one may attempt to use the existing analytical base of copper, molybdenum, gold and silver analyses to make element abundance and element ratio studies of the Tintaya ores that might reveal ore distribution and zoning patterns useful for guiding mineral exploration, thus reducing detailed exploration and development costs.

The Huancarama Sur, Ccayo-Huinicunca and Ccoyme-Fito prospects are not of the copper-gold skarn type. Hence, they most likely would require different process circuits to be integrated into the Tintaya operations, but would have to stand on their own. The most attractive of these prospects is Ccoyme-Fito, which merits further study.

Las Bambas

The Bambas zone represents an important geologic resource area which is currently in an early stage of development. Although prospecting and minor development has taken place for most of this century, there has been no significant production. PAH believes that this zone offers good potential for discovery of new deposits and expansion of existing resources.

The Bambas area is located in the northwestern end of the 250 kilometers long belt of major copper-gold skarn deposits that stretches from Tintaya to the city of Abancay. It is called "Bambas" because the best known ore deposits in this area are named Ferrobamba, Chalcobamba and Sulfobamba, all part of the privatization package reviewed in this report. However, these are only three out of eleven copper-gold skarn deposits occurring in close proximity in the department of Apurimac. The others are Charcas (also a subject of this privatization package), Pallanja (= Antillano), Paraíso, Colca, Yuringa, Yanaminas, Antamarca and Buena Fé.

The Ferrobamba, Chalcobamba, Sulfobamba and Charcas deposits are alike and similar to the Tintaya ore deposits in being copper-gold skarns resulting from the metasomatism of the Ferrobamba formation by dioritic and monzonitic intrusives.

The four deposits under consideration have been evaluated on the basis of surface geological mapping and sampling, limited tunneling, geophysical surveys in all four deposits, at least six churn drill holes in Ferrobamba and six diamond drill holes in Chalcobamba.

The sparce information available has been compiled at various times to arrive at ore estimates of variable reliability (Table 2-2), but which give at least an idea of the tonnages and grades one may expect in this group of deposits.

It is PAH's opinion that the Bambas area has excellent potential for the discovery of significant resources at a grade in the range of two to three% copper. Widespread copper-gold mineralization is exposed at the surface, but drilling to date has consisted of only 12 holes. A considerable amount of additional drilling is needed to evaluate the true potential of the Bambas area.

Winicocha

The Winicocha disseminated prospect is located about halfway between the Tintaya and Bambas areas (68 kilometers NW of Tintaya, 80 kilometers ESE of the Bambas, and 20 kilometers ENE of the Katanga district described below). The prospect was mapped geologically and sampled (227 samples), revealing stockwork type mineralization in an intrusive within a 3.8-kilometer long and 750-meter wide area. This mineralization consists mainly of quartz and gold-bearing pyrite, with subordinate amounts of galena and chalcopyrite.

In addition, within this stockwork there are some veins up to 250 meters long and widths between 0.2 and 4 meters, estimated to contain about 4.7 million tons of 0.24 grams Au per ton. Outside of the stockwork there are up to nine veins with lengths between 200 and 1,100 meters and widths between 1 and 20 meters, adding up to about 4.9 million tons with grades between 0.21 and 0.84 grams Au per ton. Within

Table 2-2


this total the bulk consists of 3.0 million tons with 0.23 grams Au per ton and 1.3 million tons of 0.56 grams Au per ton.

PAH emphasizes that these are preliminary resource estimates only.

Coporaque

The Coporaque prospect is located about 15 kilometers due west of Tintaya. It consists of a number of veins in diorite and quartz-monzonite intrusives. The mineralization consists of quartz, pyrite, gold, galena, chalcopyrite, boulangerite, luzonite, tetrahedrite and galenobimutite. The main structure is the Tambonate vein, which crops out over a distance of 450 meters and has an average width of 1.6 meters (although underground it appears to be 1.8 to 2.3 meters wide). Its northern ore- shoot is estimated to contain 25,000 tons with an average grade of 10.8 grams Au per ton, 2.7 ounces Ag per ton, 0.9% Cu and 1% Pb.

3.0 MINING AND RESERVES

The Tintaya area consists of several deposits with significant development drilling completed and one open pit referred to as Tajo. Tajo, which is the primary ore production unit, has been in operation since 1985. A site location map is shown in Figure 3-1.

The deposits are referred to as Tajo (remaining ultimate pit), Inflexion, Chabuca Este, Chabuca Sur and Coroccohuayco. The Inflexion and Chabuca Este deposits are primarily a continuation of the east-west trending mineralization from Tajo. In terms of mine planning, the Inflexion deposit has not been separated as a distinct mining zone due to its close proximity to the existing open pit. In fact, the Inflexion mineralization is what helped push the ultimate pit of Tajo to the south and west, as will be discussed later.

In order to develop a mine plan, the deposits must be evaluated in terms of their open pit versus underground potential. Since a clear decision cannot be made early in the evaluation stage of which mining method is more economic, PAH evaluated all the deposits in terms of both an underground and open pit scenario. The resulting estimates (mine reserves, capital and operating costs) were compared using the net present value method to guide the valuation study. The analysis serves as a guide for determining the development scenario. The results indicate that an open pit at Chabuca Este might have significant economic advantage.

Not only is the evaluation concerned with maximizing present value, but meeting mill production requirements as well. With this in mind, PAH selected a scenario which consists of mining the remainder of Tajo as an open pit, excavating portions from the

Figure 3-1


ultimate pit walls and beneath the pit floor (3845 level) via underground methods, mining Chabuca Sur as an open pit mine, and extracting ore from Chabuca Este and Corroccohuayco as an round operation.

Even though PAH has selected this particular scenario, it behooves the operator to further evaluate, in more detail, the Chabuca Este and Corroccohuayco deposits in terms of open pit and/or underground optimization plans to maximize the Tintaya resource potential. Further optimization may enhance the open pit operation at Tajo.

Engineers for Tintaya have developed a mine plant for Tajo based on similar design parameters used by PAH. The major exception is that they steepened the pit slopes to 49 degrees in contrast to the 45 degrees recommended by PAH. As would be expected, this resulted in significantly less waste tonnage (about 35 million tonnes) over the life of the pit. Over 1 million tonnes of high-grade ore on the lower benches is also sacrificed. Although PAH does not fully endorse the Tintaya mine plan, it represents one alternative that an investor may want to consider.

Reserves for the Tintaya have been calculated for the mine areas discussed above. Table 3-1 summarizes the mineable reserve as of September 1, 1993. The total conceptual mineable reserve is based on a combination of open pit and underground mining activities. Additional exploration and mine optimization could change the reserve status, most likely by increasing the reserve base.

Production from Tajo is scheduled to continue through the year 1998. At that time, ore mining would commence at Chabuca Sur open pit where ore mining is scheduled through the year 2000. Table 3-2 details the conceptual production schedule for the entire project area.

Table 3-1

Table 3-2 (foldout)

When the Tintaya pit production is complete, underground mining of deposits located within the pit walls can commence. For the Tintaya underground ores located below the ultimate pit bottom, the development of the Chabuca Este haulage tunnel and an access ramp will need to be completed before they can be mined. Nevertheless, PAH recommends that this project be delayed until economic conditions improve.

Production from Chabuca Este and Coroccohuayco is needed to meet the production goal of 2,800,000 MT for the year 2001. The first year of production is usually less than the scheduled full production rate due to the "learning curve" that exists at all newly developed mines. Therefore, in order for Chabuca Este to produce at a rate of 1,400,000 MTPD in the year 2001, production must begin in the preceding year. Production has been scheduled to begin with 800 MTPD in the first quarter and then build up by 800 MTPD each quarter, i.e., 1,600 MTPD in the second quarter, 2,400 MTPD in the third quarter, and 3,200 MTPD in the fourth quarter. The next quarter would begin year two and would be at the full production rate of 4,000 MTPD. This gradual buildup would result in an average production of 2,000 MTPD in the first year.

With an estimated three years preproduction development time required for mine and infrastructure development, development for this mine will need to begin in the beginning of 1997.

With a full production of 4,000 MTPD (1,400,000 MTPY) scheduled from Chabuca Este in the year 2002, a production rate of 4,000 MTPD is also required from Coroccohuayco each year until the Chabuca Este reserves are depleted in year 2008. At that time, ore production will be supplemented by underground production from Tintaya at a significantly reduced throughput.

As at Chabuca Este, the start-up production at Coroccohuayco will be less than the scheduled full production rate due to the "learning curve". However, because of the experience grained at Chabuca Este, only two quarters have been estimated to reach full production at Coroccohuayco.

At Coroccohuayco the pre-production development period has been estimated at four years, so work will need to begin at the same time as the Chabuca Este development, or at the beginning of 1997, in order for the mine to be ready for production in 2001.

4.0 PROCESSING

The ore processing facility at Tintaya is a conventional crushing, grinding and flotation plant. Principal operating parameters of the plant are presented in Table 4-1. Figure 4-1 shows the facility layout.

The plant is a very rugged, heavy duty design intended to operate for decades with low operating and maintenance costs. SNC of Montreal, Canada was responsible for the design, procurement, and construction management. The concentrator was commissioned in 1985 and has been well maintained. The plant is in good condition.

Concentrator

The ore in the coarse ore stockpile is recovered by three vibrating feeders which feed onto a conveyor leading to the fine crushing plant. In the fine crushing plant there are three seven-foot Symons cone crushers, one standard and two shortheads. There is a vibrating screen ahead of the standard crusher and vibrating screens on the discharge of all three cone crushers. All the screens are 7- x 20-foot double-deck units with half-inch openings on the bottom decks. Screen undersize is conveyed to the fine ore stockpile. Oversize on the screen ahead of the standard crusher is fed to that crusher; oversize of the screens located on the discharge side of the crushers is recycled to the shorthead crushers.

Fine crushed ore is reclaimed by variable-speed belt feeders which discharge onto two parallel belts that feed the two primary grinding circuits. The primary grinding circuits consist of 3,000 horse-power, 16- x 20-ft overflow ball mills closed with four 26-inch cyclone (two operating, two standby). The cyclones are fed by fixed-speed, 12- x 10-inch Warman high-chromium-alloy slurry pumps. Primary mill grind is between

TABLE 4-1

Tintaya Mine

Principal Processing Parameters

Item

Units

Value

Ore Processing Rate

 Annually

 Daily

Ore Grade

 

tonnes/year

tonnes/day

percent Cu

 

2,800,000

8,000

2

Copper Recovery

 Ore processing

 Smelter payable

 

percent

percent

 

89.5

96.5

Concentrate Grade

 Copper

 Silver

 Gold

 

percent

oz/tonne

oz/tonne

 

31.5

4.5

0.15

Operating Costs

 Plant

 Freight, smelting, and refining

  Charges

  Precious metal credit

 

$/tonne ore

$/lb payable Cu

$/lb payable Cu

 

6.00

0.32

0.080

Concentrate Impurities

 Iron

 Sulfur

 Lead

 Zinc

 Arsenic

 Antimony

 Bismuth

 Alumina (Al2O3)

 Lime (CaO)

 Magnesia (MgO)

 Molybdenum disulfide (MoS2)

 Cadmium

 Mercury

 Fluorine

 Chlorine

 Silica (SiO2)

 

percent

percent

percent

percent

percent

percent

percent

percent

percent

percent

percent

percent

parts/million

percent

percent

percent

 

18-20

21-24

0.01-0.04

0.01-0.09

0.01-0.05

0.01-0.04

0.01-0.02

0.60-1.90

4.00-5.10

1.70-1.92

0.10-0.20

0.002-0.004

1.0

0.003-0.009

0.001-0.003

10.0-14.0

 


Figure 4-1


50 and 60% minus 200 mesh and the particle size of the cyclone overflows are measured by on-stream particle-size analysers. Mill control is manual.

The ore is floated in a simple rougher and cleaning circuit. Eight 38-cubic-meter Otokumpu cells are used in the rougher and rougher scavenger circuit and eight 300-cubic-foot Denver cells are used in the cleaner circuit. Part of the rougher concentrates are reground in a 450 horse-power, 9- x 12-foot overflow ball mill closed with six-inch cyclones. A small (1-meter diameter x 12-meter high) pilot column cleaner cell is incorporated in the cleaning circuit. The column cell has been shown to give marginally better results than conventional cells.

The concentrate is pumped to a 100-foot diameter thickener and the tailings to cyclones. Tailings cyclone overflow is thickened in two 250-foot diameter thickeners. Concentrate and tailings thickener overflows are recycled to the mill, constituting about 50% of the plant water requirements.

Thickened concentrate is pumped to a 6- x 5-meter agitated storage tank and is then filtered in four Otokumpu Larox pressure filters. The filters have needed a great deal maintenance and have, until recently, produced a filter cake with a relatively high moisture content (between 12 and 13%). Recent innovations, primarily eliminating the interconnecting piping between filters, has resulted in substantially lower moisture content in the cake, and it is expected that it will be possible to maintain a moisture content of about 10.5% in the future.

The concentrate filter cake is conveyed to a storage area which consists of a large covered area with 12,000 tonne capacity and an adjoining open patio. The concentrate is loaded by 6.5-cubic-yard capacity scoop tram into 20-25-tonne capacity highway trucks for overland transport to the Southern Peru Copper Corp. smelter at Ilo and to the port of Matarani for export to other custom copper smelters. The trucks are weighed on a truck scale located at the entrance to the plant area.

The Tintaya processing staff have and are currently investigating several promising projects to improve production, efficiency, and product quality, the principal of which are as follows:

     Pre-conditioning of slurry ahead of rougher flotation. It is believed that the flotation time is barely adequate. To counter the problem, an agitated tank that was formerly used for lime slurry is being modified for this service and will be placed in operation shortly.

      Flash flotation in the primary grinding circuits. Investigations indicate that this is worthwhile and has the potential to improve concentrate grade and reduce concentrate moisture content, the latter as a result of producing a coarser concentrate product.

      Computer control of the primary grinding circuits. Instrumentation is in place to allow computer control of the grinding circuits. Implementation of computer control will almost certainly result in higher throughput, increased efficiency, and improved flotation performance.

     On-stream x-ray analysis and computer control of the flotation circuit. The single-product flotation system lends itself to a installation of a simple, reasonably inexpensive, on-stream analysis and control system which would maximize the economic operation of the flotation circuit.

      Column or Jameson cleaner flotation cells. The pilot column cell has shown a slightly better performance than the conventional cells. It is likely that a complete column or Jameson cell cleaning circuit would improve concentrate grade.

Tailings Containment

Tailings flow by gravity to pump boxes from which they are pumped to 20-inch cyclones (4 operating, 2 standby). The coarse, high-density cyclone underflow is laundered to various points where it is placed in front of intermediate dikes within the containment area that have been built of monzonite waste rock or borrow material. The cyclone overflow flows to the two tailings thickeners where it is thickened and separately laundered to discharge within the diked zones in the containment area. In this way the capacity of the tailings area is maximized.

The tailings containment system, as originally designed, was to thicken the tailings and deposit the thickened slurry at the upper part of the dam furthest from the dam wall so as to build up the solids at the upper end and with a slope of at least 1.5% and thus maximize the solids content of the structure. The system did not work as planned; tailings slurry flowed all the way to the dam wall with a very shallow slope, and in so doing filled the containment much more quickly than anticipated.

To provide additional tailings storage capacity, the main dam wall, which is built of monzonite waste rock, was raised by a further addition of monzonite waste rock, this time using upstream construction. A drawing showing a cross-section through the newly raised dam wall is presented in Figure 4-2. At the same time that the main dam wall was raised, the pumping and cycloning system for the thickened tailings was installed and the system of intermediate dikes investigated.

Figure 4-2


Decant water from the intermediate dikes flows to the main dam wall where it collects and seeps through the wall and flows in the natural drainage a distance of about half a mile to enter the Salado river, just downstream of the river pumping station. The water is normally clear, though there is occasional turbidity, primarily at the time of heavy rainfall, and at such times part of the decant water usually flows out via the dam spillway in addition to that seeping through the dam wall.

Storm water run-off is directed away from the dam by a ditch located upstream of the open pit and which runs to natural valleys on either side of the containment area.

A study of the tailings system is currently in progress. This is being conducted by the Universidad Nacional de Ingeneria in conjunction with Centro Peruano de Investigaciones Sismicas y Mitigacion de Desastres and the Laboratorio Nacional de Hidrologio. Results of this study are due in December 1993.

Projected remaining life of the tailings containment using the new system is through the year 2005 though PAH considers this optimistic. In the judgement of PAH, a more realistic projected life is through the year 2000, but even this will require careful management so as to maximize storage in the upper reaches of the containment area. In case of unexpected difficulties and for the long term operation of the mine, planning will need to begin shortly for a completely new tailings containment area. There is ample available land in the vicinity and it should not be particularly difficult to find additional suitable tailings containment sites.

Provision is made in the cash flow analysis for new tailings facilities in the year 2000 and for future sustaining capital for those facilities.

Utilities and Services

Power for the plant is supplied by ElectroPeru with stand-by power supplied by the on-site generating station. Mainline power is subject to frequent outages, especially in stormy weather. Such unplanned outages result in considerable spillage in the grinding area.

Water is supplied by the pump station on the Salado river, though half of the plant requirements are obtained by recycling water recovered in the concentrate and tailings thickeners. The water supply is plentiful for most of the year but, towards the end of the dry season, it is just adequate. Any significant expansion of mill capacity would probably require an additional source of water.

Assaying services are provided by a laboratory that is managed by the administrative department of the company. Sample preparation is conducted in a sample preparation facility in the mill building.

There are two maintenance shops serving the processing facilities, one within the mill building and one in a separate building. In addition there are several areas adjoining the process buildings which are dedicated to maintenance work.

Mobile equipment is serviced by the company vehicle maintenance shops. The shops also provide truck cranes when needed and machining and major electrical equipment servicing.

Freight, Smelting and Refining

Tintaya concentrates have been custom smelted at a number of smelter sites worldwide. The current year's production is largely committed to smelters in Peru (Ilo and La Oroya) and Brazil. Tintaya concentrates are unusually clean, with no elements present at levels that would have a deleterious effect on any copper smelting operation or cause unusual environmental problems; they also contain appreciable quantities of precious metals.

In order to reach overseas markets or Centromin's La Oroya smelter, concentrates are trucked either directly to the port of Matarani or transhipped to rail at Canahuas, 150 km from the mine site. Concentrates smelted locally are shipped by road to the Ilo smelter. For all destinations, the first 150 km of road from the mine site are the most difficult and probably lead to the greatest element of inland freight costs. Truck loads are limited to 20-25 tonnes and large numbers of contractor owned trucks are continuously employed in shipping concentrates. The use of rail freight should be capable of reducing inland freight costs, but the existing contract with the state-owned railroad is extremely unfavorable. Only minimum contract commitments are transported by rail.

Past and projected costs of freight, smelting and refining are summarized in Table 4-2 which shows a marked decline in FSR costs in recent years, almost all attributable to decreased transport and other domestic costs. Total FSR costs have fallen from 49.5¢/lb in 1990 to 34¢/lb in 1993 and are projected to fall to 32¢/lb in 1994. In summary, 1993 freight, smelting and refining costs average U.S.$0.34/lb payable copper, while payable precious metal credits add U.S.$0.08/lb to the value of payable copper.


TABLE 4-2 Tintaya Mine

 Concentrate Production and Freight,

Smelting and Refining Costs, 1990 - 1992

 

 

 

 

1990

1991

1992

1993

(Contracted)

1994

(Projected)

Concentrate Produced:

 

 

 

 

 

   MT wet (x1000)

144.8

166.6

178.1

 

 

   MT dry (x1000)

128.8

147.7

157.9

 

 

   Average % moisture

12.4

12.8

12.8

10.0

 

   Average % Cu

31.5

31.7

31.7

31.0

 

Freight, Smelting and Refining:

 

 

 

 

 

Sales

119.8

138.6

161.3

165.0

 

Total contained Cu (Mlb)

83.2

96.8

112.7

112.7

 

Total payable Cu (Mlb)

80.4

93.5

108.9

108.8

 

Costs:          Inland Freight  

M U.S.$

6.2

9.3

10.1

6.0

 

 

U.S.$/lb

0.077

0.099

0.093

0.055

0.04

   Other Sales Costs

M U.S.$

10.3

4.3

2.6

0.7

 

 

U.S.$/lb

0.128

0.046

0.024

0.006

0.01

   Treatment & Ocean

M U.S.$

14.1

16.5

19.0

19.4

 

    Freight

U.S.$/lb

0.176

0.176

0.174

0.172

0.19

   Refining

M U.S.$

9.1

10.7

12.6

11.82

 

 

U.S.$/lb

0.1136

0.114

0.1161

0.1087

0.08

Deductions (% of total Cu)

3.4

3.4

3.4

3.3

 

Total FSR, U.S.$/lb

0.495

0.435

0.407

0.342

0.32

 


5.0 INFRASTRUCTURE

As a result of the remote location of Tintaya, the mine is provided with a very complete infrastructure, including housing and services for all employees.  A general site map showing the general layout of the production and infrastructure facilities is shown in Figure 5-1.  Principal components of the infrastructure are as follows:

       Access routes

       Power supply

   Fuel supply

       Water supply

       Buildings

       Mobile equipment

       Communications systems

Access Routes

The main transportation route used by the mine is that which connects Tintaya with Matarani, a 370-kilometer road, having two sections: Tintaya-Arequipa section with 260 kilometers having a compacted gravel surface which is in an average condition, and the Arequipa-Matarani section with 110 kilometers of asphalt surface in good condition.

The connection between Lima, Nazca and Arequipa forms part of the system of the southern Panamerican highway, which is asphalted in its entirety and is in average condition.

Cuzco and Tintaya are interconnected by means of a 2560‑kilometer compacted gravel surface road which is in average condition.

Figure 5-1

Power Supply

When Tintaya commenced operations in late 1984, all power was supplied by Tintaya's own diesel-electric generating plant (16.2 MW).  This continued for about 18 months when, following the installation of a power transmission line from the state hydroelectric power plant at Machupicchu, power was provided (12 MW) from this source.  The hydroelectric power is provided at a much lower cost than that which can be generated on site.  The power plant at Tintaya is in excellent condition and is used periodically when there are interruptions in the mainline power supply.

The electrical system that serves Tintaya is part of the state power company, ERSESA, which supplies the power through SISE (Sistema Interconectado Sur Este).  The power is supplied on the basis of a two-year written contract.

Water Supply

The demand for fresh water for the Tintaya mine, which amounts to about 100 liters per second, is provided from two sources: the first, from the Salado river, which amounts to 96% of the supply, is used for both industrial and potable services; the remainder, which comes from seven springs located in the upper reaches of the Tintaya stream valley, is exclusively used for potable water.

The flow in the Salado river, which occurs year round, amounts to approximately 1,000 liters per second in the dry season and about 200,000 liters per second in the rainy season.

The mine has authorization to take a maximum of 400 liters per second from the Salado river and to pump eight liters per second from the springs.

In addition to fresh water supply, about 128 liters per second of water is recycled and reutilized within the ore processing plant.

Administration

Administration requirements for Tintaya are extensive, primarily as a result of the remote location of the mine.  The largest employee group is that for operations comprising 516 of the total 907 employees.  The employees which are directly part of administration are the Administration group and the Accounting and Finance group.

6.0 ENVIRONMENTAL REVIEW

An environmental review and assessment of operations of the Tintaya facility was performed in September 1993. This work involved a detailed file review at Tintaya's main office in Lima followed by an assessment, using World Bank standards as guidelines, of the mine facilities near Yauri.

The project can best be described as located in a semi-arid, high altitude (+4,000 meters above sea level), altiplano type environment.

Generally, the Tintaya project can be characterized as a modern facility with environmental controls that approach North American standards. Notable exceptions include the geotechnical stability of the pit wall, the geotechnical stability of the tailings impoundment, and the disposal of solid waste/lab waste and used oil and solvents.

Listed below by section are critical environmental components of the Tintaya facility. Assessments and recommendations, where applicable, for each component are discussed.

Geotechnical

The tailings dam was designed by Robinsky Associates of Toronto, Canada and was originally designed for a downstream extension. In fact, an upstream extension has been incorporated. The original design also called for a limestone, rock filled dam that allowed for limited seepage. However, the facility is currently holding excessive amounts of water.

Tintaya personnel have attempted to minimize the adverse impacts of this design by the creation of miniature dikes within the tailings impoundment and diversion dikes on the peripheral edges of drainages coming into the tailings impoundment.

In early september 1993, the consulting company of CIS MID had the following comments to make on the tailings facility:

     1.       Outside slopes needed to be graded to 1.7:1 versus the current 1:1 ratio.

     2.       Tintaya needed to locate the source of material of competent rock for the dam extensions.

     3.       Tintaya needed to correct filtration problems in the dam face.

     4.       Tintaya needed to make sure that the canal or diversion was designed to handle 60 liters per second.

     5.       Tintaya needed to drill the foundation of the dam itself to ensure that it was geotechnically stable.

     6.       Tintaya needed to eliminate the use of escorellos (floating dams) as they were only a temporary measure. These are considered to be unstable and one had already disappeared.

     7.       Tintaya was instructed to improve the storage capacity and design of the emergency pond. This included increasing the dam face and the relocation of the canal on the berm.

None of these activities appeared to have been initiated during our visit later on in the month. Tailings stability and capacity are being reviewed by Universidad Nacional de Ingeneria.

Tintaya also needs to look into the geotechnical stability of the southeast portion of the mine pit area. During the course of our visit, the upper portions of the pit wall were sliding down into the pit at what appeared to be a rather fast rate. Diversion ditches have been constructed in an attempt to keep surface waters from saturating the soils and making them more unstable.

Solid Waste

Solid waste disposal can be broken down into three categories:

     1.       overburden

     2.       refuse

     3.       septic/sewage

The placement of waste rock/overburden at the Tintaya facility is being carried out according to acceptable industry norms. The geochemistry of the rock appears to be good with no visible signs of acid generation. This is apparently due to the excess amounts of limestone (buffering capacity) available in the waste rock.

Tintaya disposes of all solid waste/refuse in the waste dump. However, there is no specific area designated for this. It would be advisable to set aside a certain portion of the waste dump for this activity. The purpose of this recommendation is to have access to the area should problems with disposed items come up.

The sewage treatment at the Tintaya facility was a very modern state-of-the-art designed facility. However, during the course of our visit, it was evident that the capacity of the facility was exceeded at times. Visible signs of nutrient enrichment in and near Rio Tintaya were observed.

Water Resources

On a positive note, Tintaya's water treatment plant provides a good source of drinking water to the employees and their families. This water meets all applicable drinking water standards.

However, current practices with regards to the disposal of hydrocarbons (used oil and solvents) by direct discharge onto land surfaces and the disposal of lab wastes into the sewage treatment system could have an adverse effect on surface and groundwater quality in and around the project area.

Air Quality

Tintaya's mitigation of air quality impacts is extremely efficient. The utilization of water trucks for dust suppression on haul and access roads, coupled with the covered coarse ore stockpiles, have a positive effect on visual air quality.

The utilization of scrubbing systems in the crushing circuit also are some of the best units on the market. However, one practice that could be improved upon is the disposal of fines that are collected in the scrubbers. Currently this material is piled outside of the scrubber facilities and is ultimately discharged into Rio Tintaya. It is recommended that this material be put into the mill circuit, minimizing any adverse effects and recovering additional metal value.

Socio-Economic and Cultural Resources

Tintaya has done an excellent job of providing an improved standard of living for the local people. These improvements are seen in the education system, health system, as well as improvements in the personal wealth.

In addition, Tintaya also allows for the relocation of displaced herders to an encampment that has such facilities as clean drinking water and electricity.

Vegetation, Wildlife Resources

The impacts on vegetation and wildlife resources are considered minimal, in that the only adverse effects are those impacts directly associated with the facilities. The natural vegetation includes high altitude grasses and shrubs that are important to area livestock.

Only avian species of wildlife were observed. However, there appear to be no adverse impacts on these species. In fact, the tailings impoundment water storage area served as a resting point for numerous migratory species.

Reclamation and Closure

Interviews with Tintaya personnel confirm that no reclamation plan or closure plan existed for the facility.

In order to satisfy World Bank guidelines and standards, it would be advisable to develop closure/reclamation plans for implementation during and after the facility is mined out. It is evident that livestock can be supported in the surrounding area. By careful planning, opportunities for the stockpiling of service topsoil can take place. Many species of livestock forage have been adapted to upper elevation sites throughout the world. These include alfalfa, rye grass, trefoil, and foddering turnip.

7.0 PROCESS ALTERNATIVES

PAH has based a conceptual development plan on two major principals. First, although there are important proven and probable ore reserves, significant time and expense will be required to develop this to the production stage. There are, fortunately, sufficient developed reserves in the Tajo to allow enough time to proceed with the orderly development of these new mining areas. Additionally, there is good reason to believe that new reserves will be found through additional exploration and effectively extend the mine life.

The second major principal is that Tintaya, like any operating mine, must continually strive to lower its cost structure. Although its current cost of USD 0.57 places it at the bottom half of the cost curve, the introduction of new processing technology can have significant positive effect. A number of processing alternatives exist whereby costs may be reduced, additional production might be achieved or value added by producing and shipping metal rather than concentrates.

Concentrate Treatment

The combined costs of freight, smelting and refining of concentrates constitute approximately 45% of the total costs of copper production. The production of metal, in the form of blister or anode copper, at the mine site presents the potential for savings in overall production costs. The viabilility of on-site metal production will be, to a considerable extent, dependant on the operating life of the facilities and the rate at which they may be amortized. This, in turn, is dependant on the reserve base of the area. It is possible that reduction in operating costs by on-site metal production will positively affect cut off grades and therefore reserves. In addition, some of the processing alternatives considered for the production of metal from sulfide concentrates also present opportunities for low cost sulfuric acid production, which may substantially improve the cost of copper production from oxide reserves.

Traditional pyrometallurgical methods of metal production from sulfide concentrates demand substantial economies of scale for viability; the current concentrate production rate at Tintaya and the probable constraints of future underground mining methods indicate that the economies of scale required for traditional smelting methods will not be achieved. However, emerging pyro-metallurgical techniques have been developed to the stage that relatively low cost metal production at rates comparable to those anticipated at Tintaya has been achieved. In addition, well established combinations of pyro and hydrometallurgical processes are possibly applicable to Tintaya concentrates, while less developed hydrometallurgical processes are worthy of consideration. The following list, although not exhaustive, summarizes potentially applicable processes:

1.       Continued production and shipping of concentrates for custom smelting.

2.  On-site flash smelting of concentrates.

3.       Submerged combustion smelting of concentrates (known commercially as Sirosmelt, Ausmelt or Isasmelt).

4.       Roasting and sulfuric acid leaching of concentrates.

5.       Ammoniacal leaching of concentrates.

6.       Bacterial leaching of concentrates.

7.       Nitric/sulfuric acid leaching of concentrates.

Of the above processes, bacterial leaching and nitric/sulfuric acid systems are considered unproven at the industrial scale at this time, while ammoniacal leaching is unlikely to be appropriate for the suite of minerals in the Tintaya concentrates. PAH examined the other technologies and have concluded that submerged combustion smelting offers the best chance of economic and technical viability.

Submerged combustion smelting is an emerging technology that has been successfully applied at an industrial scale and has shown potential savings in capital costs relative to flash smelting for small to medium sized operations. Unlike a flash smelter, in which fast reaction kinetics are achieved by oxidation of sulfides in gas suspension, the sulfides are introduced, together with fuel and air or oxygen enriched air, below the surface of a pool of molten matte and slag. This is achieved by means of a lance that is protected by frozen slag. The resulting reactions are not only extremely fast, but do not require the volume of the reaction shaft of the flash furnace. Relatively small, low cost furnaces are therefore required.

It is possible to use a single vessel for both smelting, which is a continuous process and converting, which is a batch process. However, this gives rise to great fluctuations in gas flows. If a sulfuric acid plant is operated, better control of gas flows is obtained by operating separate vessels or conventional converters. Flow of matte from smelting to converting vessel may be in liquid or granulated form.

Enrichment of air by gaseous oxygen may be advantageous but is not necessary even at the altitude of Tintaya. The major advantages of oxygen enrichment are a smaller furnace, lower fuel consumption, lower offgas volumes and offgas richer in SO2 . The major disadvantages are the high capital cost of the oxygen plant and the power consumption required for oxygen production. This study addresses smelting with and without oxygen enrichment, but this subject requires study in much greater detail.

Oxide Treatment

Several possible treatment approaches have been considered for Tintaya oxide ores. On the basis of the test data available and the recommendations in the COMMSA oxide ore feasibility study of 1988 and the Kilborn feasibility study of 1989, an oxide ore pilot plant was constructed during the period between June 1988 and January 1990, largely with used equipment. The pilot plant was operated between February 1990 and December 1991.  The objectives for operation of the pilot plant were defined by Tintaya as follows:

1.  To confirm, at a larger scale, the results previously obtained in order to support the development of basic and detailed engineering for construction of the full-scale plant.

2.  To better define the hydrometallurgical process for the treatment of Tintaya oxide ores, studying the alternatives of agglomeration, curing and leaching in load-unload thin layers versus leaching separately of the coarse and fine portions of the ore.

3.  To define the principal operating parameters.

4.  To verify the use of leaching, solvent extraction, and electro winning at a larger scale.

5.  To train future administrative staff, as well as supervisors and operating personnel.

Although all of the laboratory scale testwork conducted in conjunction with the pilot plant showed that ores had good permeability to leach solution and extraction of copper in 8 to 12 days with moderate acid consumptions, difficulties were experienced at the pilot plant, in part because of economic constraints that did not allow for the installation of an improved heap loading system, especially in conjunction with drip irrigation of the leach heaps.

The elevated content of natural clays and the disintegration of both coarse and fine ore during curing and leaching considerably decreased the permeability of the ore. The high natural moisture content of the ore (12% in summer and 18% in winter) interfered with the correct adjustment of moisture in the curing and agglomeration process unit operations and limited the use of solvent extraction tailings solution (raffinate) to adequately dilute the concentrated acid introduced ahead of the agglomerator.

The direct leaching circuit was operated from January 25 through September 21, 1990. The test results indicated that direct leaching is not a viable alternative because of lack of permeability of the ore. It is believed that the carbon dioxide gases generated during leaching flowing upward through the material and the plugging of the ore under treatment caused leach times to be in the range of 60 to 77 days, and lowered the extraction of copper.

A flowsheet using agglomeration and curing of the ore ahead of leaching This system was operated from September 22, 1990 until December 1991 when the pilot plant was shut down. Two ore irrigation systems were studied, watering with sprays, and drip irrigation. Drip irrigation resulted in better operation and recoveries than watering with sprays.

In order to better establish the treatment parameters for Tintaya oxide ores, PAH agrees with the Tintaya engineers working on the oxide project that the oxide ore treatment pilot plant should be reactivated.


8.0 CONCEPTUAL DEVELOPMENT PLANS-PRODUCTION, COSTS AND INVESTMENTS

PAH has evaluated three processing scenarios. Scenario 1 is a continuation of the current situation, i.e. concentration with shipment to custom smelting. Scenario 2 is a continuation of Scenario 1 but with the addition of copper recovery from oxide material through leaching and SX/EW recovery. Sulfuric acid for leaching would be bought off-site and transported to Tintaya. Scenario 3 involves the construction of a submerged combustion smelter (e.g. Sirosmelt) to treat Tintaya concentrates. Sulfuric acid would be generated on-site and used in acid leaching of oxide material. This would result in a significant reduction in freight and smelting charges.

Mining

The development plans for all three Scenarios are presented in the following series of tables. Scenarios 1, 2 and 3 all assume the same mine development sequence and the delivery of 2.8 million tons per year (8000 tpd) to the concentrator. Table 8-1 illustrates the mine sequence.

Mine production will continue in the Tajo until 1998 when it will move to Chabuca Sur. Open Pit production will continue through 2000 at Chabuca Sur. Underground development for Chabuca Este and Coroccohuayco will begin in 1997 which will allow enough time for them to be in full production by year 2001. Mining at a rate of 1.4 million tonnes annually from each of these deposits can continue until 2008 based on current reserves. Coroccohuayco will have a few years of ore still available after this.

Mining from areas under and beside the current Tajo are not programmed into this schedule.

Table 8-1

Annual mine operating costs are shown in Table 8-2. They are based on the following unit costs:

       Surface Mining       USD 0.90 per tonne (increased to USD1.00 after 1996)

       Chabuca Este        USD 9.50 per tonne

       Coroccohuayco       USD 12.50 per tonne.

NB: All costs are in 1994 USD

Coroccohuayco costs are higher due to increased lifting and hauling costs.

Mine operating costs will climb from the USD 18 million forecast for 1994 to over USD 30 million by 2002. This cost is directly related to the movement from open pit to underground mining. It is compensated by higher ore grades.

Significant expenditures will be necessary to develop the known mine reserves. Table 8-3 shows the equipment and infrastructure costs associated with each operation. Table 8-4 shows the mine development costs.

The total anticipated equipment and infrastructure capital cost to allow mining to continue over the next 15 years is USD 119 million. Mine development costs are forecast to be USD 38 million over the same period. The combined total is USD 157 million. The majority of this (USD 137 million) will have to be spent between now and 2000 to insure sufficient mill feed.

PAH has previously explained that optimization of mine planning and consideration of open pit mining at Chabuca Sur may have a significant positive impact on the amount and timing of capital expenditures. Further study is called for and PAH strongly recommends that this be considered.

Table 8-2

Table 8-3

Table 8-4

Scenario 1: custom smelting of concentrates

 Scenario 1 assumes a continuation of the current practice of custom smelting of concentrates. The concentrator production schedule is shown in Table 8-5. Although mill feed is kept constant at 2.8 million tonnes annually, concentrate production climbs from 166,270 tonnes in 1994 to 223,360 tonnes by 2002. This is a direct function of the higher ore grades anticipated from Chabuca Este and Coroccohuayco.

Concentrator operating and capital costs are shown in Table 8-6. Annual operating costs are based on a unit cost of USD 6.00 per tonne of ore processed. Capital costs are for sustaining capital and some plant modification with the exception of new tailings capacity. A new investment of USD 7.5 million will be required by the year 2000 to insure adequate tailings capacity.

General, Administrative and Marketing expenses are shown in Table 8-7. Annual G&A costs are fixed at USD3.5 million. Although these costs appear modest in comparison to many operations it should be pointed out that Tintaya accounting policy allocates certain G&A costs back to the mine and mill areas. This results in those areas being slightly higher than might be expected. PAH has continued with this policy in its cost estimation. Annual FSR costs are based on a unit cost of USD 0.32/lbCu copper payable. This includes all inland freight, ocean going freight, smelting and refining charges.

Scenario 2: custom smelting of concentrates plus recovery of copper from oxide resources

The second alternative development plan, Scenario 2, maintains concentrate production as described but also includes recovery of copper from oxide resources. Table 8-8 presents anticipated oxide copper production as well as the forecast production and investment costs.

Table 8-5

Table 8-6

Table 8-7

Table 8-8

Full scale production would begin in 1997 processing 910,000 tonnes of ore per year and continue through the life of the project. Initial production would come from the existing high grade stockpiles. However subsequent processing of lower grade materials would result in a drop of production. There are potential but unquantified higher grade resources that could be substituted for the low grade material in later years. Initial production is expected to be 17,000 tonnes annually. This will continue for six years before dropping off.

Total capital expenditures, including the operation of a pilot plant for two years, are forecast to be approximately USD 56 million. Annual operating costs of USD 11.4 million is based on a unit cost of USD 12.94 per tonne ore processed plus USD 0.43 per tonne material from the existing stockpiles of 10 million tonnes to leaching areas. Cathode freight costs of USD 60 per tonne are additional to the operating costs.

Scenario 3: construction of smelter on site

The construction of an on-site submerged combustion smelter combined with sulphuric acid production and recovery of oxide copper is modeled for Scenario 3. Concentrates will be treated on-site to produce blister copper which will be shipped for refining. The smelter production schedule and costs are shown in Table 8-9. This scenario results in the same total copper production as Scenario 2.

This Scenario has the advantage of eliminating custom smelting charges and lowering freight costs due to shipment of higher value added products. Also sulphuric acid would be generated as a by-product which can be used in the oxide recovery process. This would eliminate the USD 80 per tonne acid cost included in Scenario 2. This advantages are partially offset by higher on-site operating cost (smelter costs).

Table 8-9

Annual smelter operating costs vary between USD 13.5 and USD 17.5 million. This is based on a unit cost of USD 0.1231 per pond of copper in blister. Blister refining charges are USD 0.11/lbCu payable copper. Blister freight charges are estimated at USD 60 per tonne. Based on a purity of 97.5% this translates into USD 0.028/lbCu copper. The total FSR charges under Scenario 3 are therefore USD 0.26/lbCu. This represents a reduction of USD 0.07 from custom smelting. Annual savings are approximately USD 7-8 million depending on the volume of copper produced.

The cost to produce oxide copper will also drop under this scenario as acid is generated as a byproduct of smelting. This would eliminate the estimated USD 80 per tonne cost for delivered acid. Copper oxide production costs would drop substantially from the USD 12.94 per tonne ore treated ( Scenario 2) to USD 7.39 per tonne treated. This results in an annual saving of about USD 5 million.

The cost savings will not come without a price. The investment expense is estimated to be USD 64.4 million. PAH emphasizes that this Scenario is conceptual and substantial investigation will be required before its feasibility is proven.

9.0 VALUATION

PAH has taken a two-fold approach to the valuation of Empresa Minera Tintaya S.A. Its first approach uses discounted cash flow methods to determine a present value of the company. The second approach is to use comparable transactions as the basis for determining a "market-based" value. Ultimately the real value of the company is what someone is willing to pay for it, i.e. this is the true market value. By adopting the twofold approach PAH is able to determine a range of reasonable values that can be used as the basis of negotiations with potential investors.

PAH has not used an "asset-based" approach to valuation because it believes that this often results in an exaggerated value for the company.  Many of the fixed assets, such as buildings or earthworks, have value only if the mine is in operation.  If the mine ceases operation then the building will cease to have any value because of its remote location.  Essentially, the only true "asset" value is the liquidation or salvage value of the fixed assets and inventories.  This is often only a small fraction of their depreciated or "book" value.

PAH has applied its valuation methodology to two distinct operational areas: The Tintaya Mine with its nearby deposits (Chabucas, Coroccohuayco) and other areas (Las Bambas, Katanga, etc).

The two valuation methodologies are appropriately applied to the Tintaya area. Cash flows are based on  production parameters and costs that can  reasonably be quantified. The historical data and the relatively high level of engineering input allows forecasts to be made with confidence. In regards to the comparable transaction analysis there are a sufficient number of similar transactions to allow reasonable comparisons to be made.

The other areas present a different problem. They are all considered to be exploration prospects and therefore any forecast of future production or costs would be so speculative it would have no meaning.  PAH does not consider discounted cash flow techniques suitable for this situation.

There are a number of comparable transaction for similar exploration properties. Their value, however, if often based on some future "option value" to be realized if exploration is successful. It is PAH's experience that any agreement is likely to be structured  to allow the  investor to commit to a spending program with an option payment made only if a positive production decision is made. A typical agreement might require the investor to spend increasing annual sums on exploration and feasibility studies until a future date. If these commitments are not made the property would be returned to the owner. At the future date, the investor would decide whether to purchase the option at the previously negotiated price or return the property rights to the owner.

PAH has decided to assign only a minimal value to the other areas. It has maintained the comparable transaction approach under the assumption that this represents a certain amount that will be paid for the exploration rights.

Cash Flow Calculations

Cash flow models for the three cases described in Section 8.0 have been constructed. The first cash flow model is the base case - continuing to operate the mine at its current rate of 2.8 million tonnes of sulphide ore per year and shipping the concentrates elsewhere for custom smelting. The second model allows for processing 910,000 tonnes of stockpiled and in-situ oxide ore annually through an SX/EW circuit and producing cathodes on-site. Acid for use in the SX/EW circuit is purchased at a delivered cost of $80 per tonne. The treatment of 2.8 million tonnes per year of sulphide ore, and off-site custom smelting continues. The third model incorporates the SX/EW circuit plus an on-site submerged combustion smelter for smelting all concentrates and producing acid for use in the SX/EW circuit. The operating parameters for the three cases are summarized in Table 9-1. All three cases have project lives of 15 years.

 

TABLE 9-1

       Summary of Operating Parameters for Cases 1,2 and 3

 

 

Production

 

Operating Costs

Capital Spending

       Case

000's tonnes ore/yr

 

MM lbs Cu/yr

 

$/tonne ore

 

$/lb Cu

 

MM $

1 - Base Case

2,800

125

30.80

0.57

120

2 - Addition of SX/EW Circuit

3,710

147

27.76

0.55

149

3 - SX/EW + On-site Smelting

3,710

147

25.04

0.51

187

 

All three cases begin in 1994 and continue until 2008. At this point it is assumed that the mine is closed and all remaining equipment is sold at salvage value. Even though the production schedule shown in Table 2.2.6-2 of Volume II shows enough ore to last until 2021, it is in the year 2009 that total ore production falls from 2.8 MM tonnes/yr to 1.75 MM tonnes/yr and total production continues to fall to 105,000 tonnes/yr in 2015. While the potential for finding more mineable reserves is good, there are not enough currently known reserves to keep the concentrator at full capacity past 2008. Operating costs would become unreasonably high with the concentrator operating at only half of its capacity.

The NPV's for the projected cash flows in cases one, two, and three are shown in Table 9-2 using a range of discount rates from 20% to 10% per annum. The results of the analysis indicate that Case 2, with the addition of the SX/EW circuit, has marginally higher NPV's ranging from US$65.8 MM to $US142.3 MM.  It is interesting to note that there is little variation in NPV among the three cases.  The major difference is the unit operating cost (per pound of copper) which decreased from US$0.57 (Case 1) to US$0.51 (Case 3).

TABLE 9-2

Tintaya Project

Net Present Values

($ 000's)

 

 

 

 Discount Rate

Case 1

Case 2

Case 3

20%

63,521

65,884

53,181

17.5%

73,902

78,857

657,851

15%

86,980

95,154

86,546

12.5%

103,633

115,811

110,508

10%

125,083

142,250

141,488

Sensitivity Analysis

A sensitivity analysis was performed on the cash flow models to investigate the reaction of the present value of the three projected cash flows to changes in copper price, capital costs, and operating costs. The results are shown in Table 9-3, using a real discount rate of 15%. The value of the project is most sensitive to changes in commodity price. It is also sensitive to changes in operating cost. Changes in capital cost have relatively small effects. All three cases show positive NPV's when copper price is $0.75/lb. This is encouraging since copper price recently reached a low of $0.72/lb but is currently trading at $0.80/lb as of this writing.

TABLE 3.1-7

Tintaya Project

Results of Sensitivity Analysis

 

 

 

 

 

 

NPV's at 15%Discount Rate

 

Case 1

Case 2

Case 3

 

Copper Price

 

 

 

 

$1.05

152,582

171,629

163,043

 

$0.90

86,980

95,154

86,546

 

$0.75

19,814

17,961

7,493

 

Capital Cost

 

 

 

 

+15%

77,557

82,515

68,522

 

Base

86,980

95,154

86,546

 

-15%

96,402

107,703

104,352

 

Operating Cost

 

 

 

 

+15%

41,130

43,330

37,112

 

Base

86,980

95,154

86,546

 

-15%

131,834

145,414

134,680

 

Comparable Transaction Analysis-Tintaya Area

To establish a basis for the value of the Tintaya mine, a comparable transaction analysis was completed using recent transactions of copper reserves in South America. The comparative transaction approach to valuing an asset consists of collecting price, quantity, and quality information on recent sales of similar assets. The price, quantity and quality information is used to deduce a value for the asset in question. For the Tintaya mine, the results of a similar comparable transaction study by PAH, completed in 1992 was reviewed. This study analyzed copper property transactions from 1985 to April of 1992 and gives a reasonable range of unit prices (US$/lb. Cu in reserves) in which to expect the unit price for the Tintaya mine to be.

Next, information was gathered on sales of copper properties in Peru and Chile from May of 1992 through October, 1993. Specific information gathered included property names, location, ore type (sulphide/oxide), reserve tonnage, reserve grade, reserve classification, mining method, operating cost, production rate,% of ownership transferred, cash paid in the transaction, and the names of the buyers and sellers.

To begin the analysis, the characteristics of the Tintaya project must be assessed so that reliable comparisons to other, recently traded properties can be made. The Tintaya mine is an open-pit mine with a concentrator. Underground mining is planned for exploiting a portion of the reserve. It is the world's highest open-pit copper mine, located in the Andean altiplano at an elevation of 4,100 meters. The Tintaya mine went into production in 1985 with a development cost of $315 million. The mineable reserves (proven and probable) currently stand at 48.2 million tonnes of sulphide ore at a grade of 2.4% Cu and a stockpile of 9.86 million tonnes of oxide ore at a grade of 1.61% soluble Cu. Currently, all ore is processed through a modern mill, and trucked 370 km to the port of Matarani for export. The concentrates are sold to a variety of smelters in the region.  Annual production rates of contained Cu in concentrates is between 110 and 125 million pounds. The production of an additional 35 million pounds of cathode copper through SX/EW processes is possible but will require a capital investment of $47 million.

A study of acquisition costs for copper properties was completed by PAH in the Spring of 1992. A total of 147 transactions were analyzed in the period from 1985 to 1992. Property locations were world-wide excluding the CIS and China. The median price paid for copper properties exhibiting the major characteristics of Tintaya are shown in Table 9-4.  The unit prices, stated in US cents/lbCu Cu contained in reserves, range from 0.31 to 5.69.


TABLE 9-4

Tintaya Project: Comparable Transactions

 

 

 

 

Summary from 1992 PAH Study Median Acquisition Costs for the Following Copper Property Characteristics

1st Quarter 1992 Cents/lb Cu

3rd Quarter 1993 cents/lb Cu

Premium/Discount from Dataset Median

 

 

Median Value of 147 Cu Property

Transactions from 1985/1992

Properties in Chile Production Stage

Properties with both Sulphide and oxide Ore

For Proven and Probable Reserves

For Average Ore Grades >2.00%

For Total Contained Cu Between 2.5 B lbs and 5 B lbs

Open Pit Mine

Acquired Interest (100%)

AVERAGES

1.42

1.13

2.82

0.30

2.34

2.46

0.73

1.76

0.97

1.46

1.16

2.90

0.31

2.40

2.53

0.75

1.81

1.00

1.59

0.00%

-20.42%

98.59%

-78.87%

64.79%

73.24%

-48.59%

23.94%

-31.69%

9.00%

Pertinent findings of the study indicated that discounts were taken below the median price of 1.46 cents/lb Cu for properties located in developing or politically unstable countries. Unfortunately, none of the transactions in the database were for Peruvian properties. Chile was used as a proxy for location. Premiums were paid for properties already in production, since the level of confidence in costs and production rates is much higher than for properties in exploration or development. A discount is made for properties having both sulphide and oxide ore, most likely due to the higher capital cost incurred in having two ore processing facilities on site. Premiums are paid for certainty of reserves and for reserve grades greater than 2% Cu. Premiums are also paid for reserves in excess of 10 billion pounds of contained Cu and for properties exploitable by surface mining methods. Discounts were taken for purchase of 100% acquired interests and premiums were paid for 10% to 30% acquired interests.

In light of the study, the positive aspects of the Tintaya mine are that it is an operating mine producing very clean concentrates, ore reserves have been established with a high degree of certainty, the average grade of reserves are greater than 2%, and it is an open pit mine. The detrimental aspects of the Tintaya mine are its location in Peru, a country known for political uncertainty, remoteness of the site and the high cost of concentrate haulage, the relatively small size of the deposit, the necessity of building an SX/EW facility to treat oxide ores, and that 100% of the mine is for sale. From the PAH study, a premium of 10% is indicated for the Tintaya property above the median purchase price of 1.46 cents/lb Cu for all 147 transactions. This results in an adjusted price of 1.61 cents/lb Cu for the Tintaya property. This can be regarded as the high range of possible value for the Tintaya property. If this factor of 1.61 cents/lb Cu is multiplied by the mineable reserves of 2.92 billion lbs Cu at Tintaya, the resulting value is US$47 million.

The next part of the analysis of comparable transactions was to gather information on all comparable copper property sales since the Spring of 1992. During this time, the governments of Chile, Peru, and Argentina all liberalized investment policy for development and exploitation of domestic mineral resources by foreign, private companies. This resulted in numerous transactions of mineral properties occurring in the last year. Table 9-5 shows the transactions for which public information was available. The sale of the Lince mine in Northern Chile by Outokumpu was not included here due to a large portion of the sale price representing the cost of the mill that Outokumpu built. Since all of these transactions took place either in Peru or Northern Chile, these will be used as the set from which comparative prices will be estimated.

Table 9-5

Two Peruvian properties, Cerro Verde II and Quellaveco, were sold in the last year. The weight-average price per lb Cu in reserves paid for these properties was 0.3 cents. The weight-average price for the four transactions in Chile was 2.2 cents.

Even though Cerro Verde II is in Peru, it has significant differences to Tintaya that preclude using its transaction price as a comparable. The Cerro Verde deposit is over twice the size of Tintaya, with a reported reserve of 8.7 billion lbs Cu. However, the grade of the ore is less than half that of Tintaya. The mine is close to a major city, Arequipa, were there is rail haulage access to Matarani, 85 kilometers away. Similarities to Tintaya are that both oxide and sulphide ore are processed, the property is currently in production at a rate of 68 million lbs. Cu/yr, and it is a surface mine.

Quellaveco is closer to Tintaya in reserve size (6.3 billion lbs Cu.), however, Quellaveco has no known oxide ore. It also has much lower grades (0.8%) than Tintaya. It is undeveloped and its reserves are still classified as "geologic". Quellaveco has the advantage over Tintaya of being closer to rail transportation and a port.

The Ivan property in Northern Chile is comparable to the Tintaya mine in several ways. The average grade of the Ivan reserve is 2.52%, it has both sulphide and oxide ore reserves, and a combination of surface and underground mining are planned for exploiting the reserve. Unlike Tintaya, however, the Ivan property is within 100 kilometers of a port city (Antofagasta) and the reserve is smaller (262 million lbs. Cu).

The combined characteristics of the three copper properties above come reasonably close to matching those of the Tintaya mine. The one characteristic that they are missing is Tintaya's remoteness. A weight-average of the unit price for the three properties above results in a price of .37 cents/lb Cu. The discount for Tintaya's remoteness is hard to quantify. A subjective estimate of a market value for the Tintaya mine is .3 cents/lb Cu. This results in a value of US$8.76 million for the Tintaya property. This value can be regarded as the low range for the value of Tintaya.

Since the Tintaya mine is currently in production and producing cash flow, its value should fall within the high portion of the range between US$8.76 million and US$47 million. A premium for the mine is warranted since a new owner could begin making money from the mine the day it is purchased. No large amount of up-front capital is needed to get the mine into production.

Comparable Transaction Analysis - Other Areas

PAH has considered only  Las Bambas  in assigning value to the other areas outside of the Tintaya and surrounding district. The other concessions controlled by the company can only be considered as early exploration prospects.  Most have only some surface exploration and no or little drilling to quantify resources. For these reasons, PAH believes that potential investors will fully discount their value.

As discussed above, PAH believes that the speculative nature of future development in  Las Bambas makes their value minimal in comparison to the main area of interest, i.e. the Tintaya district. Never-the-less the amount of historical work has allowed a preliminary quantification of resources which in turn creates some current value.

Resources in Las Bambas have been calculated during previous periods of exploration, mostly by the Cerro de Pasco Corporation and Mitsui Corp. This resources were presented in Section 2. A summary of the relevant numbers is presented below:

         Mt ore      Grade %      M lb Cu

Chalcobamba        10.200           2.2 %          494.6

Ferrobamba           8.300           2.1 %          384.2

Sulfobamba           3.100           1.3 %          88.8

Total      21.6           2.0 %          967.6

Using the same transaction database discussed above, PAH has determined that an average value of US$ 0.00

75/lbCu of contained copper in resource for all thirty properties in the exploration stage of development. PAH believes that a substantial discount should be applied for the area's remote location (and correspondingly high infrastructure requirements) and its location in Peru. PAH has applied a 50% discount to determine a common value of US$0.0038/lbCu contained copper. Applying this multiplier to the resource base a value of US$ 3.7 million is indicated for Las Bambas.

PAH emphasizes that this value is highly speculative and that many investors will be more inclined to pay it at some latter date upon the exercise of a development "option".

Total Value

As discussed in the introduction to this section PAH emphasizes that the value of any mining project is based on a complex set of investor perceptions. These include many factors such as metal price expectations,  possible reserve expansion, new operating efficiency and the introduction of new technology to increase production or lower costs. Individual investors will bring a different set of expectations and perceptions to their own concept of the property's value. It would be impossible to anticipate all of these different possibilities.

From the sellers point of view it becomes necessary to anticipate a reasonable range of values upon which to base any subsequent negotiations. PAH, in its valuation has taken a multifaceted approach to provide such a range. The cash flow analysis is based on a specific set of operating assumptions. These can either be fully accepted by the investor or remodeled to suit their personal perspective. Although PAH believes that the US $0.90 copper price used for the base case projections is reasonable over the long term it may clearly be an area of controversy. Investors may use a lower price or assume a higher discount rate to accommodate the perceived higher risk. This could substantially reduce the net present value.

The comparable transaction method attempts to incorporate investor perceptions as indicated by historical market activity. It is a useful methodology but any adjustments made to place transactions on a truly comparable basis may be questioned. Regardless, PAH has found that this methodology tends to provide an accurate indication of market value. Based on the previous discussion, PAH believes that a market value of US$ 40 million is appropriate.

Results from the above analyses are summarized below:

       NPV (15% discount)            Base Case   US$ 87 million

       Comparable Transaction (Tintaya)            US$ 40 million

       Comparable Transaction (Las Bambas)            US$ 3.7 million

A combined indicated value of US$ 43.7 to 90.7 million is indicated.

IV. PROPERTIES, FACILITIES AND PRODUCTION

IV.A.     General

The Tintaya mining concession is located in the "Ferrobamba Copper Belt" which extends in a NW‑SE direction over a distance of 500 km between Arequipa and Cusco and covering parts of the departments of Cusco and Apurimac in southern Peru. Tintaya's concession is located in the SE corner of the copper belt, 260km NW of Arequipa and 250km SE of Cusco, just off the national road which links Arequipa to Cusco, through Canahuas, Negro Mayo, 16km south of the town of Yauri.

The "Ferrobamba Copper Belt" contains a variety of metallic orebodies which are related to the Andine uplifting i.e. copper, copper‑gold‑silver, lead‑zinc‑gold‑silver, gold, iron. Tintaya is the only active copper mining operation in the copper belt but there are several other concessions owned by private companies, including the Japanese Mitsui which holds a concession on a porphyry type orebody.

IV.B.     Geological resources

Known geological resources in Tintaya's concession are distributed in four main areas explored as of today; they are referred to as Tajo, Chabuca Este, Chabuca Sur and Coroccohuayco. Tajo is the open‑pit mine in which Tintaya first started mining operations in years 1983‑1985 but which is nearing depletion (4‑5 years are left). Chabuca Este, Chabuca Sur and Coroccohuayco are prospects for the continuation of present mining operations. The former are continuous and adjacent to Tajo, the latter is situated 8 km away, to the SE. All these orebodies are volcanic intrusions in sedimentary formations, which have been transformed into skarn type mineralisation by contact metamorphism.

The combined copper resource of the four areas, as quantified by the present status of drilling and sampling work, is summarised as follows in million of metric tonnes (Mt) and copper grade (% Cu) at the cut‑off grades selected (see later):

     Sulfides          61.4 million tonnes          2.50 % Cu

     Oxides          23.5 million tonnes          2.15 % Cu

     Total          84.9 million tonnes          2.40 % Cu

Oxides represent more than 25% of the total resource; approximately 10 Mt have already been extracted during the process of mining Tajo and are stockpiled on the mine site for future development which will require special treatment.

In addition to copper, the sulphide ores contain significant gold and silver values which can be recovered in traditional pyro-metallurgical processes. The ores produced by Tajo since 1985 have shown gold and silver values of 0.2‑0.3 g/t and 8‑10 g/t respectively (or 4.5 g/t and 150 g/t in the concentrates produced).

The exploration potential in Tintaya's concession is reportedly good. It appears highly possible that quantified resources would be substantially increased by continued exploration. In this respect, Tintaya's experience since Tajo started operations in 1985, clearly demonstrates that additions to the reserve inventory, have considerably exceeded the quantities of ore extracted, as a result of continuous exploration effort.

Neighbouring Tintaya, there are two other copper concessions. Quechuas, 8km to the SSE, belongs to the Japanese company Mitsui; this is a porphyry copper orebody with an estimated 80 Mt of ore and an average grade of 0.85% Cu. Antalaya, 3km SSW, belongs to a private owner; it is a similar orebody as Tajo with a quantified resource of 2 Mt of ore and a grade of 2% Cu.

Other important exploration areas exist outside Tintaya's concession. The most important of these is an area known as las Bambas, a Quechua word for plateau. Significant copper and gold mineralizations are known owing to remote geological campaigns, geochemical surveys, ground sampling, drilling and underground workings the latter being limited in extent. Detailed and extensive exploration work has so far been limited by the more remote location of this area; indeed, it is located some 300 km NW of Tintaya (100km SW of Cusco). However, it definitely represents a potential resource for future development. Such development is dependent on infrastructures.

Minable reserves in Tintaya's concession, have been estimated for the four main areas known today. The Tajo and Chabuca Sur orebodies are considered to be mined as as open pit operations. Chabuca Este and Coroccohuayco are considered to be exploited as underground operations. However, it is realised that the future owner may wish to consider openpit mining also for Chabuca Este and Coroccohuayco, depending on the outcome and results of additional exploration and cost planning. Considering the current costs of ore extraction and of concentration at Tintaya's Tajo mine and concentrating plant, and with estimates of underground costs of extraction derived from experience in Peru, cut‑offs of 0.65% Cu and 1.45% Cu have been determined for openpit and underground operations respectively.

Minable reserves have been established using these cut‑off grades. Minable reserves for the four areas are presented overleaf (table IV-1):

Table IV-1

IV.C.            ORE EXTRACTION

IV.D.            ORE CONCENTRATION

Tintaya operates a concentrator which produces 32% Cu concentrates from the ore mined. The present capacity of the concentrating plant is 8 000 t/day or 2.8 Mt/annum. The plant is in excellent condition both in technology and in state of maintenance; moreover, its capacity could be easily increased to 12 000 t/day or 4.2 Mt/annum, with marginal investments.

The copper concentrates produced by Tintaya from Tajo openpit feature good metallurgic quality, with low or no content of deleterious elements e.g. As, Hg etc

Mineral processing is by conventional sulphide flotation (8 000 tonnes/day) to produce a copper concentrate. The concentrate is trucked to either the smelter at Ilo or to the port of Matarani for shipment overseas. The production parameters for 1993 are the following.

Ore Processed       2.8 Mt

Ore Grade       1.96 % Cu

Metal recovery       89.7 %

Concentrate Produced       158 000 tonnes

Concentrate Grade       31.62 % Cu

Add-on precious metals       150 g/t silver

                   4.5 g/t gold

Transport costs are approximately 22 USD:t of concentrate, to which 10 USD/t are added for port handling charges, and 30‑40 USD for sea freight, or a total of approximately 60‑70 USD/t of concentrate, which corresponds to 0.09‑0.10 USD:lb Cu.

Current smelting contracts result in a smelting and refining charge of approximately US$0.22/lb Cu. Precious metal (Au and Ag) credits are about 10% of Cu sales value..

The Tintaya mining area contains all the necessary infrastructure to support the openpit mine and the concentrator, i.e. a maintenance workshop, stores warehouses, reserve power generating plant (17MW), field offices and general administration blocks. In addition there is a mine township which includes all necessary amenities: hospital, school, shops, recreational facilities, chapel. Lodging facilities comprise of separate sets of bungalows for engineers and employees while housing for workers is provided in multi‑level appartment blocks situated in the main township area.

Power is supplied from the State Hydroelectric Plant of Machupicchu (12 Mw) via a high voltage transmission line (140 kV). A reserve diesel powered generating plant (8 units with a total power of 17 MW) is also available. This plant was initially meant to provide the full power requirement of mine and concentrator (main users being the mine's cable loaders and the concentrating plant's mills and flotation cells). After, connection with the national electricity grid, the full reserve value of this generating plant has become particularly useful. Indeed, the mine and concentrator are fully reliable with regard to possible power trip‑offs from the network. Power trip‑offs can indeed considerably affect the operation of the concentrating plant by imposing costly clean‑ups and circuit emptyings, with damaging effects on metal recovery and concentrate quality and grade. The existence of reserve generating capacity, capable of taking full load and immediately in case of a power trip‑off is therefore an important plus for the future owner of the property.

Ample water supply is available from the nearby Salado river, where the main pumping station is situated.

The project is run in an environmentally sound manner although certain issues must be addressed. Dust from scrubbers should be recycled into the mill circuit. A closure plan does not exist. The tailings facility is currently holding excess amounts of water.

Current operating costs at Tintaya are US$0.57/lbCu copper (net of precious metal credits). A number of alternatives have been reviewed to lower the cost structure. These include the addition of acid leaching and SX/EW recovery of copper from oxide resources and the construction of a submerged combustion smelter to treat concentrates on site. Although these alternatives are conceptual in nature, unit costs have been forecast. Acid leaching can reduce costs to US$ 0.56/lbCu. On site smelting would further reduce costs to US$ 0.51/lbCu. These are average prices over the life of the known reserves.