| Nilefos Minerals Limited: Phase I: Capital cost summary | |||||
| US$ (000) | |||||
| Mining equipment | 8,658 | ||||
| Beneficiation of ore to concentrate | 30,121 | ||||
| Delkor scope | 10,469 | ||||
| Infrastructure and civil EPCM | 19,653 | ||||
| Fertiliser production complex | 57,788 | ||||
| Tailings Dam/Fe3O4 heap contingency | 1,000 | ||||
| Infrastructure and Owners costs | 10,338 | ||||
| Financing charges | 16,000 | ||||
| Legal and financial Fees | 4,000 | ||||
| Pre-start interest | 12,000 | ||||
| EIA Resettlement Action Plan | 18,500 | ||||
| Total Project Cost | 142,405 | ||||
| Operating cost summary | |||||
| Annual production of enriched rock phosphate mt | 200,000 | ||||
| unit cost of production of rock phosphate US$/t | - | ||||
| cost of mining US$ (000) | - | ||||
|
|||||